geo

Existing Customer / Network Modification

Increase of capacity

Customer is obliged to notify System Operator on request for increasing the capacity connecting to the distribution network. In such case, customer is obliged to address System Operator with request “On increasing the electricity connecting capacity by the customer” (Request standard form is approved by the commission upon decision). This request form is also used when there is the request of the customer on moving (changing) to the higher voltage level.

Discussion of the application “On increasing the electricity connecting capacity” by the customer and satisfying shall be carried out with that rule and terms as determined by articles 17 and 18 of the rules if other cterm of service by this article is not defined.

Customer is obliged to pay 50 % of the fee for increasing the electricity connecting capacity represented into the request form before submission of application “On increasing the electricity connecting capacity”. Payment of the rest amount by the customer should be done within 5 working days from the day when the works are completed, if the parties did not agree on other terms for payment of the cost in written form (in material or electronic form).

System Operator is obliged to state the compliance of the request and request indicated in it within 10 working days from request receipt and notify applicant immediately on response, as by SMS, also through electronic way as given into the request or in case of establishing the material error, refusal should be confirmed. In opposite case, request (application) will be considered as received. In case if the error is stated into the request, System Operator has to return to the customer paid amount within 10 days term on the account indicated into the request.

If the customer of 0,4 kv (380/220 v) and 6/10 kv voltage increases electricity factual connecting capacity by more than connecting capacity foreseen by the technical specification in such way that change of connecting technical specification is needed or/and requires move(change) to the high voltage stage, in such case issuance of the new technical specification should be done by System Operator and also organization of electricity supply system of this customer (provision with the entire technological cycle) in line with the new technical specification requirements, herewith, customer shall pay the cost for increase of electricity connecting capacity that is calculated in the following way:

a) If the increased (requested) capacity or/and requested voltage stage goes to the other offered package of new object connection to the distribution network, customer shall pay the cost for relevant package of new object connection to the distribution network, minus the cost determined by that offered package for new object connection that is in compliance with the connection capacity defined by technical specification of existed connection of the customer;
b) If the requested capacity does not exceed the scope of that offered package of new object connection to the distribution network with what connecting capacity determined by existed connection technical specification of the customer is in compliance:

b.a) For supply of requested capacity it is necessary to reconstruct of electric network and metering knot connecting to this customer by System Operator or/and purchase of the other facilities, construction and installing. Customer shall pay the cost that is calculated per each kW, cost of corresponding connecting offered package of new object connection to the distribution network divided to the maximum capacity of this package and multiply to additionally requested kW by the customer.

b.b) If the capacity supply requested by the customer does not need reconstruction of electric network and metering knot connecting to the customer, or/and purchase of the other facilities, construction and installing, than payment of the cost by the customer is not done.
In cases foreseen by the subparagraphs “a” and “b” of Paragraph 5 of this article, System Operator is obliged to satisfy customer’s demand on capacity requested by the application within the term determined by package offered by Rules N2 and annex.

If customer requested such capacity on what the fee for capacity increase is not spread, in such case, process should be carried out with the same rule and terms as defined in case foreseen by the paragraph 18 and 17 of these rules. Despite by whom the works foreseen by this article is performed, for organizing the metering knot and cutting works, payment should be done in accordance with the offered packages “cost of organization of metering knot” defined by the rules and Annex No 3.

If there is a request on electricity connecting capacity increase on 6/10 kv voltage stage by connecting capacity less than 501 kW capacity or at 35/110 kv voltage by the connecting capacity less than 5001 kW, such request can be met only deriving from the technical necessity of the customer (person who wants capacity increase), if organizing of metering knot at lower voltage is impossible. The mentioned paragraph is not spread on connecting capacity increase on that same voltage stage of 6/10 kv and 35/110 kv voltage customers.

Annex № 2


 
Voltage step kV
 
 
 
 Capacity kW
Dates of connection of a new object to the distribution network
connection dates (Period)
 
 
Fee for connection of a new object
including VAT (GEL)
 
 
self-governing cities
 
Other Municipalities
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
0,4
 
10 (1-10 kW 220 V)
 
40
 
60
600
 
10 (1-10 kW 380 V)
 
40
 
60
1800
 
from 10 to 30
 
40
 
60
7000
 
from 30 to 50
 
40
 
60
10500
 
from 50 to 80
 
40
 
60
13000
 
from 80 to 100
 
40
 
60
14500
 
from 100 to 120
 
40
 
60
16500
 
from 120 to 150
 
40
 
60
18000
 
from 150 to 200
 
45
 
60
39000
 
from 200 to 320
 
60
 
90
56000
 
from 320 to 500
 
60
 
90
86000
 
from 500 to 800
 
90
 
110
136000
 
from 800 to 1000
 
90
 
110
170000
 
from 1000 to 1300
 
90
 
110
221000
 
from 1300 to 1600
 
90
 
110
272000
 
from 1600 to 2000
 
90
 
110
340000
 
from 2000 to 2600
 
90
 
110
442000
 
from 2600 to 3200
 
90
 
110
544000
 
 
 
 
 
 
6-10
1-500
 
60
 
90
96000
from 500 to 1000
 
90
 
110
180000
from 1000 to 1500
 
90
 
110
287000
from 1500 to 2000
 
90
 
110
350000
from 2000 to 3000
 
90
 
120
463500
from 3000 to 5000
 
90
 
120
749000
 



Bank Requisites on which should be paid the fee of new consumer’s connection to the network:

Recipient Bank: JSC “TBC Bank”

Account Number: GE32TB7015336030100006

Description: Fee of the new consumer’s connection to the network (should be indicated the name of applicant and factual address of object). 

Filled in application form for capacity increase should be sent to the following e-mail address:newcustomers@energo-pro.ge 

Application form: 

Regarding increase of electricity connection capacity by the customer 18.06.2021

Regarding increase of the electricity consumption capacity of a multi-apartment house 18.06.2021