How to become a company customer?

Power supply with micro capacity on the site in case of registration as new customer

Micro capacity power plant represents renewable power source under customer or customers’ group ownership (including the possession, lease, leasing or in other form), that is connected to the electricity distribution network by connecting to the customer internal net or directly to the distribution network. Capacity of micro capacity power plant does not exceed 500 kW.

Retail customer or group of the customers has the right to request connection of micro capacity power plant under its ownership to the distribution network of the power plant. Connection of micro capacity power plant to the distribution network is carried out with the payment condition of “micro capacity power plant connection fee” to the distribution licensee, in accordance with the requirements “electricity (capacity) supply and consumption rules”. Installed capacity of micro capacity power plant under retail customer ownership should not exceed connecting capacity of the customer to the distribution network and installed capacity of micro capacity power plant under retail customers’ group ownership should not exceed the total connecting capacity of these customers’ group to the distribution network.

a) In case of connection of the existed customer to the internal network – “fee for organizing the smart meter” defined by the Annex No 4

b) In case of micro capacity power plant connection directly to the distribution network - “fee for connection of the new object on 0,220 kV, 0, 380 kV and 6/10 to the distribution network” foreseen by the Annex No 2 and “ fee for organizing the smart meter” defined by the Annex No 4.

c) In case of requesting the use of micro capacity power plant by the customer (for organizing the smart meter) – “ fee for organizing the smart meter” defined by the Annex No 4, except the case when customer is connected to the low voltage side of common transformer point or has the smart meter;

d) In case of capacity increase when there is an increase of customer connection capacity, during the use of micro capacity power plant connected to the internal network or increase of customer capacity using the micro capacity power plant or micro capacity power plant connected directly to the distribution network – fee foreseen by the rules on capacity increase.

Annex №4

Dates and fees for setting up a smart meter

Voltage Step kV

Capacity kW

 

Dates for setting up metering system
(working days)

Multifunctional Electronic metering
System arrangement

Fee including VAT, GEL

 

Fee for arranging a smart meter,
including VAT, GEL

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

0,4

1-10 (220 V)

15

300

300

1-10

15

600

600

from 10 to 30

15

600

600

from 30 to 50

15

700

600

from 50 to 80

15

700

600

from 80 to 100

20

800

600

from 100 to 120

20

800

600

from 120 to 150

20

1000

600

from 150 to 200

20

1200

600

from 200 to 320

20

2200

2000

from 320 to 500

20

2500

2000

from 500 to 800

25

2800

2000

from 800 to 1000

25

3100

2000

from 1000 and more

25

3500

2000

 

 

6/10

1-500

25

13000

2000

from 500 to 1000

25

14000

2000

from 1000 and more

25

15000

2000





 
 
Bank Requisits where to pay for new connection:

Name of teh recipient bank: JSC TBC Bank

Account Number: GE32TB7015336030100006

Description: cost for micro capacity customer connection to the network (name of the applicant and factual address of the object).
You may send the filled in new connection form to an e-mail address: newcustomers@energo-pro.ge