Person willing to be supplied with electricity and consume it should apply the relevant Service Center of the Company with application with the purpose to be registered ascustomer. Person willing to be connected (applicant) is obliged to pay 50% of the cost for the new consumer’s connection to the distribution network represented in application before submission of the application and in case of connection of the block of flats (two or more than two) to the distribution network the person willing to be connected (applicant) is obliged to pay 100% of the full cost for the new consumer’s connection to the distribution network represented in application prior to submission of application and attach the payment document to the application.
If the real estate owned by the consumer that was supplied with the electricity was divided or block of flats was developed on its place the Rule of New Consumer’s Connection is spread on connection of the separated real estate/block of flats to the distribution network as well as correspoding cost and procedures regardless the volume of capacity the initial property was connected to the distribution network.
JSC “ENERGO-PRO Georgia” is obliged to carry out the works for connection (full technological circle) to the distribution network of 220 kv, 0,380kv and 6/10kv new consumer(s) after paying the part of fee for the new consumers connection to distirbution network within the territory it carries out electricity distirbution:
a) In case of 0,4 kv voltage new consumer – within 600 m radius from the existing 0,4 or 6-10 kv distribution newtwork:
b) In case of 6/10 kv voltage new consumer – within 6 km radius from the existing 6 km distribution newtwork.
In case of two or more than two new consumers connection to the network (new consumers electric network) as result due construction of dwelling house, enterprise or other object, the amount of connection fee (according to the offered package) should be determined in compliance with capacity to be connected foreseen by construction-project documentation of this object (these objects). At the same time the capacity foreseen per each resident consumer should not be less than 10 kW capacity foreseen for first package in Annex №4 of these Rules.
Connection fee for 0,220 kv, 0,380 kv and 6/10 kv voltage new consumer’s connection to distribution network in Self-Governing Cities and other Municipalities (From August 13, 2019).
|
|
term for new consumer’s connection (working day) |
fee of new consumer’s connection |
||
Voltage stage kV |
Capacity, kW |
In Self-Governing Cities |
Other Municipalities |
In Self-Governing Cities |
Other Municipalities |
0,4 kV |
1-10 (220V.) |
40 |
60 |
600 |
400 |
1-10 |
40 |
60 |
1800 |
1200 |
|
from 10 upn to -30 |
40 |
60 |
7000 |
4700 |
|
From 30 up to -50 |
40 |
60 |
10500 |
7000 |
|
from 50 up to --80 |
40 |
60 |
13000 |
10500 |
|
from 80 up to - 100 |
40 |
60 |
14500 |
12000 |
|
from 100 up to-120 |
40 |
60 |
16500 |
14000 |
|
from 120 up to -50 |
40 |
60 |
18000 |
16000 |
|
from 150 up to -200 |
45 |
60 |
39000 |
23000 |
|
from 200 up to -320 |
60 |
90 |
56000 |
33000 |
|
from 320 up to -500 |
60 |
90 |
86000 |
50500 |
|
from 500 up to -800 |
90 |
110 |
136000 |
80000 |
|
from 800 up to up to -1000 |
90 |
110 |
170000 |
100000 |
|
6/10 kV |
from 1-500 |
60 |
90 |
96000 |
60500 |
from 500 up to -1000 |
90 |
110 |
180000 |
110000 |
|
from 1000 up to -1500 |
90 |
110 |
247000 |
137000 |
|
from 1500 up to -2000 |
90 |
110 |
319000 |
177000 |
|
from 2000 up to -3000 |
90 |
120 |
463500 |
257500 |
|
from 3000 up to -5000 |
90 |
120 |
749000 |
416000 |
b) In case of request for joint connection of two or more than two consumers, person willing to be connected pays additional fee – 100 GEL as well (including VAT) for arranging of metering knot for each new consumer together with the cost foreseen by Annex #4 of new consumer’s connection to the distribution network. i.e in case of connection of 20 flats blocks, the person willing to be connected will additionally pay 2000 GEL for arranging of metering knot together with capacity fee to be connected determined by project documentation.
c) Simultaneously in case of 2 or more customers connection the schedule of simultaneous load coefficient of multi-flats house (residents) for gasified sector.
Number of Customers |
New Ratio |
|
2 |
0.776 | |
3 |
0.662 | |
5 |
0.56 | |
6 |
0.53 | |
9 |
0.47 | |
12 |
0.43 | |
15 |
0.4 | |
18 |
0.39 | |
24 |
0.365 | |
40 |
0.33 | |
60 |
0.3 | |
100 |
0.28 | |
150 |
0.265 | |
200 |
0.257 | |
250 |
0.251 |
Bank Requisites on which should be paid the fee of new consumer’s connection to the network:
Recipient Bank: JSC “TBC Bank”
Account Number:GE32TB7015336030100006
Description: Fee of the new consumer’s connection to the network (should be indicated the name of applicant and factual address of object).
Filled in application form for the new consumer’s connection to the network should be sent to the following e-mail address: newcustomers@energo-pro.ge
Annex: