Separation of customer/immovable property

Separation of customer/immovable property

In case of division of real estate, the new customer must pay for the full technological cycle service according to Appendix No. 3 of the Rules, and in case of division of an object with smart meters - the fee for the package offered for the installation of a smart meter specified in Appendix No. 4 (the fee provided for in Article 18, Clause 2 of the Rules in accordance with the payment procedure), if:

a) real estate connected with a power of 0 to 10 kW is separated by one real estate, and the owner of the separated real estate requests connection with a power of 0 to 10 kW;
b) When dividing the real estate of a customer connected with a power greater than 10 kW, there is an agreement between the parties on power sharing and the existing power is sufficient to supply the old and separated property with a power of at least 10 kW;

c) One or more real estates in the building are supplied with electricity (through a registered customer), there is a requirement to connect a new facility to the distribution network individually, and this facility has at least 10 kW. For power supply, it is only necessary to arrange a metering node.

In the case provided by paragraph 2 of this article, the fee for connecting a new facility to the distribution network does not apply to the restoration of the electricity supply of a facility belonging to a non-household customer, if the customer was supplied with electricity not through the system operator, but through the electric network owned by him or another person. In such a case, the restoration of electricity supply should be done in accordance with the conditions and procedures provided by Article 18, Clause 17 of the Rules.
 


Annex №4

Terms and fees for smart meter installation

 

Voltage level, kV Capacity, kW აDeadline for setting up the accounting system (working day) Cost of installing a multifunctional electronic accounting system, including VAT, GEL Cost of installing a smart meter, including VAT, GEL
0.4 1-10 (220 V) 15 600 450
1 to 10 15 1200 1000
10 to 30 15 1200 1000
30 to 50 15 1200 1000
50 to 80 15 1500 1200
80 to 100 20 1500 1200
100 to 120 20 1800 1200
120 to 150 20 1800 1200
150 to 200 20 2000 1200
200 to 320 20 2500 1200
320 to 500 20 3000 1200
500 to 800 25 3500 1200
800 to 1000 25 3800 1200
1000 and more kW 25 4000 1200
10 kV 1-500 25 13000 2200
500 to 1000 25 14000 2200
1000 and more kW 25 15000 2200

 

Bank Requisites where to pay the new connection fee: 

Recipient bank: JSC TBC BAnk 

Account Number: GE32TB7015336030100006

 

Recipient Bank: JSC "Bank of Georgia"

Account Number: GE04BG0000000609622943


Description: Cost for the registration as a customer of the separated area and new connection to the network (name of the applicant and factual address of the object).

You may send the filled in form to an e-mail address: newcustomers@energo-pro.ge