Irregular temporary connection

Irregular temporary connection

In accordance with the paragraph 6 of article 24 of “Electricity Distribution Network Rules” of Resolution No 19 of Georgian Energy and water Supply Regulatory National Commission” : Person who wants temporary connection with standard condition addresses System Operator with the standard form application on “temporary connection request” and pays the cost offered for this service by the system operator in public form in advance. Herewith, existence of standard condition does not deprive the right to the customer request connection with non standard condition upon application based on the corresponding technical specification.
 
Non standard all connections that are not foreseen by the standard connection packages. Non standard is the connection when customer himself asks for non standard connection.
 
Person who wants temporary connection with non standard condition addresses System Operator with the request of issuing the technical specification of temporary connection. System Operator reviews the application of person who wants temporary connection with non standard condition within 10 working days and issues technical specification of temporary connection that includes the point for connection to the existed distribution network, voltage stage and capacity for connection. In case of fulfillment of the temporary connection works with non standard conditions with mutual agreement, agreement between the System Operator and customer is concluded by what commitment of the parties, work due to implementation and issue of ownership/possession formed as a results of this work are precisely defined.
 

In case of temporary connection under non-standard conditions, if the requested period of temporary connection exceeds 3 calendar months, after the completion of the works stipulated in the technical conditions of temporary connection, the consumer is entitled to install the metering node himself or request the system operator to install the metering node. After the completion of the works stipulated in the technical conditions, the consumer shall apply to the system operator with a request to start electricity supply and, in case of a request for the installation of the metering node by the system operator, shall also pay the fee specified in Appendix No. 4 to the Rules for the installation of a multifunctional electronic metering system, and in case of connection with a capacity of no more than 10 kW at a voltage level of 0.4 kV, the fee specified in the same Appendix for the installation of a smart meter for the relevant package.

In the above-mentioned case, if there is a relevant request, the system operator will set up a metering node and begin supply within the period specified in Appendix No. 4 to the Rules.