Electricity Consumption in Adjara Increased by 25 % for the last one year
In year 2017 pick load of Batumi city and Kobuleti exceeded 117 MW/hrs, which is by 25% more than for the same period in 2016; cases of new connections also have been increased, enhancing demand on electricity. To satisfy the demand, it is necessary to provide new capacities, which is impossible at present due to the technical condition of HV line “Erge 1”. Mentioned line had been constructed in the 30ies of the 20th century. Therefore, capital reconstruction and repair of the line is necessary for the improvement of the line capacity at least twice; This on the other hand will provide secure and stable energy supply of Batumi and Kobuleti.